Welcome to the City of Stockton's Official Website

City of Stockton Logo

Stockton All-America City 1999

Stockton Homepage  For Residents  For Visitors  For Businesses  Helpful Resources  Contact Us  SEARCH

General contact information: 425 N. El Dorado StreetStockton, CA 95202 (209) 937-8212Submit a Question/Request

City Seal

Office of the City Clerk

  City Council
    Mayor & City Council
    Council District Map
    Council Meeting Info

  Municipal Code Index
    Chapter 1
    Chapter 2
    Chapter 3
    Chapter 4
    Chapter 5
    Chapter 6
    Chapter 7
    Chapter 8
    Chapter 9
    Chapter 10
    Chapter 11
    Chapter 12
    Chapter 13
    Chapter 14
    Chapter 15 (Repealed)
    Chapter 16
    Chapter 17

  City Records
    City Charter
    Civil Service Rules:
        Miscellaneous
        Police & Fire

    Sitemap
    Site Search

Stockton Municipal Code

Chapter 3
ADMINISTRATIVE

Part IX
BIDDING, CONTRACTING, AND PURCHASING PROCEDURES

Division III
CONTRACT PROVISIONS


SEC. 3-115. TIME OF COMPLETION:
The contract shall specify the time within which the supplies or services shall be furnished to the City of Stockton and may provide for liquidated damages for failure to comply. The City may extend such time for acts of the City of Stockton, acts of God, weather, strikes, or other circumstances over which the contractor has no control.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)

SEC. 3-116. BONDS:
Whenever the City deems it advisable, a performance bond and/or labor and materials bond may be required on any contract in an amount up to one hundred percent (100%) of the contract price for each bond. Such bonds shall be approved by the City Finance Director.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)

SEC. 3-117. FAILURE OF COMPLETION:
In case of the failure on the part of the contractor to complete the contract within the time specified in the contract or within any extension of such time as herein provided, the contract may be terminated and the contractor shall not be paid or allowed any further compensation for any work done under such contract. The City of Stockton may proceed to complete such contract either by reletting or otherwise, and the contractor and the surety, if any, shall be jointly and severally liable to the City of Stockton for all loss or damage which the City of Stockton may suffer on account of the failure to complete the contract on time.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)