SEC. 3-115. TIME OF COMPLETION:
The contract shall specify the time within which the supplies or services shall
be furnished to the City of Stockton and may provide for liquidated damages for
failure to comply. The City may extend such time for acts of the City of Stockton,
acts of God, weather, strikes, or other circumstances over which the contractor
has no control.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)
SEC. 3-116. BONDS:
Whenever the City deems it advisable, a performance bond and/or labor and materials
bond may be required on any contract in an amount up to one hundred percent
(100%) of the contract price for each bond. Such bonds shall be approved
by the City Finance Director.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)
SEC. 3-117. FAILURE OF COMPLETION:
In case of the failure on the part of the contractor to complete the contract
within the time specified in the contract or within any extension of such
time as herein provided, the contract may be terminated and the contractor
shall not be paid or allowed any further compensation for any work done under
such contract. The City of Stockton may proceed to complete such contract
either by reletting or otherwise, and the contractor and the surety, if any,
shall be jointly and severally liable to the City of Stockton for all loss
or damage which the City of Stockton may suffer on account of the failure
to complete the contract on time.
(Added by Ordinance 045-92C.S. — Effective Dec. 3, 1992)